Homes NSW - Western Sydney Medium Density Housing
Project: Homes NSW Duplex Housing
Location: Western Sydney
Scope: 32 new dwellings across 16 sites
Build Time: 2 days
System: GTT Kit-of-Parts
Delivery Model: Design, manufacture and installation
Scope
GTT was engaged to deliver 32 new Homes NSW dwellings across 16 sites in Western Sydney under a $24 million Design and Construct contract, supporting the NSW Government’s broader housing delivery program. The project includes 14 duplexes and two dual-living homes, designed to provide high-quality, family-focused social housing across multiple infill locations and managing a full end-to-end turnkey solution that includes full development approvals and pre-site works before any construction began.
Challenge
Delivering 32 homes across 16 separate sites is not a simple construction program. It requires consistency across multiple locations, tight coordination between factory production and site readiness, careful logistics planning, and the ability to respond to different 5 different council, access and site conditions.
For Homes NSW, the challenge was not only to deliver more homes faster, but to do so without compromising quality, liveability or architectural intent. For GTT, the challenge was to prove that its MMC model could operate at scale across a dispersed program, while continuing to refine installation performance from one site to the next.
Solution
GTT’s Kit-of-Parts system purpose-built for this type of multi-site housing delivery.
Through upfront design resolution, digital coordination and offsite manufacturing, GTT is producing repeatable building components with a high level of accuracy before they arrive on site. Floor cassettes, wall panels and roof elements are manufactured in sequence, quality checked in the factory and delivered to site in a planned order to support faster installation.
On site, GTT has deployed two dedicated building crews who have rapidly upskilled in MMC installation. Each crew is taking lessons from every site, from crane sequencing and panel positioning through to fixings, propping, workflow and quality assurance and applying those learnings to streamline the next day of installation.
Outcome to Date
GTT has deployed two building crews across the Homes NSW program, rapidly upskilling in MMC installation and applying learnings from each site to improve the next. The result is a faster, more coordinated installation rhythm, stronger on-site capability, and a repeatable delivery model that supports housing at scale.